Thanks Bill,
Does that mean if I log the first QSO,
then click on the caller to start the next it will work as I
want? That means I won’t start the new QSO until a second or
two into the next slot. I have issues with not being able to
double click accurately enough.
73 Phil GM3ZZA
Sent from Mail for Windows 10
On 18/07/2021 17:07, Philip Rose via
groups.io wrote:
> Normally I wait for the QSO partner
to indicate they received my RR73 before logging. If they
send me the 73, and at the same time I get called by a third
party, I will double click on the third party to initiate a
QSO with them, then log the first QSO. The new QSO fails to
set the DxCall and DxGrid values and report values. When I
log this QSO I have to check what info is missing.
>
> Also when I see a DxCall value in my
logger, I display the position on DxAtlas (either the DxGrid
or the centre of the prefix area). As this is not present in
this circumstance, I can't do this.
>
> -- 73 Phil GM3ZZA
Hi Phil,
WSJT-X only supports automatic filling in
of proposed log entry fields
for a basic sequential logging process,
i.e. you must complete one QSO,
including logging, before starting the
next. Obviously that cannot
always happen due to possibly abandoned
QSOs being revived, in that case
you must check the Loq QSO fields and
fill in any missing or incorrect
information manually.
73
Bill
G4WJS.
--
73 Phil GM3ZZA